Canada must become a global superpower
The silver lining to the US starting a trade war with Canada and regularly threatening annexation is that it has forced this country out of complacency. Indeed, I'm hard pressed to remember a time, at least in my lifetime, when patriotism and nationalism has united so much of Canada. According to a recent survey by Angus Reid, the percentage of Canadians expressing a "deep emotional attachment" to the country jumped from 49% in December 2024 to 59% in February 2025. And as further evidence of...

The bank robbery capital of the world
Between 1985 and 1995, Los Angeles' retail bank branches were robbed some 17,106 times. In 1992, which was the the city's worst year for robberies, the number was 2,641. This roughly translated into about one bank robbery every 45 minutes of each banking day. All of this, according to this CrimeReads piece by Peter Houlahan, gave Los Angeles the dubious title of "The Bank Robbery Capital of the World" during this time period. So what caused this? Well according to Peter it was facil...
The story behind those pixelated video game mosaics in Paris
If you've ever been to Paris, you've probably noticed the small pixelated art pieces that are scattered all around the city on buildings and various other hard surfaces. Or maybe you haven't seen or noticed them in Paris, but you've seen similarly pixelated mosaics in one of the other 79 cities around the world where they can be found. Or maybe you have no idea what I'm talking about right now. Huh? Here's an example from Bolivia (click here if you can't see...

Canada must become a global superpower
The silver lining to the US starting a trade war with Canada and regularly threatening annexation is that it has forced this country out of complacency. Indeed, I'm hard pressed to remember a time, at least in my lifetime, when patriotism and nationalism has united so much of Canada. According to a recent survey by Angus Reid, the percentage of Canadians expressing a "deep emotional attachment" to the country jumped from 49% in December 2024 to 59% in February 2025. And as further evidence of...

The bank robbery capital of the world
Between 1985 and 1995, Los Angeles' retail bank branches were robbed some 17,106 times. In 1992, which was the the city's worst year for robberies, the number was 2,641. This roughly translated into about one bank robbery every 45 minutes of each banking day. All of this, according to this CrimeReads piece by Peter Houlahan, gave Los Angeles the dubious title of "The Bank Robbery Capital of the World" during this time period. So what caused this? Well according to Peter it was facil...
The story behind those pixelated video game mosaics in Paris
If you've ever been to Paris, you've probably noticed the small pixelated art pieces that are scattered all around the city on buildings and various other hard surfaces. Or maybe you haven't seen or noticed them in Paris, but you've seen similarly pixelated mosaics in one of the other 79 cities around the world where they can be found. Or maybe you have no idea what I'm talking about right now. Huh? Here's an example from Bolivia (click here if you can't see...
Share Dialog
Share Dialog
Back in May, I wrote a post about time to market and managing costs in condominium projects. What I wrote then remains true and equally, if not more, important today. But given all the uncertainty that we are continuing to see in the market, I thought I would elaborate on a few points.
It used to be the case, when I first started working on condominium projects back in 2007 or so, that you would go pens down on your design drawings while you launched pre-sales and worked toward meeting your construction financing requirements.
Once you hit 50% sales, or maybe once you completely reached your financing hurdle, you would then call your architect back up and kindly ask them to get started on working drawings.
And the reason you did it this way was because working drawings are kind of expensive and so you wanted to make sure that your sales were going to be there. You were also trying to push as many of your costs out to after you had your construction loan in place so that you had a lower peak equity requirement.
You can't do this today.
Since the beginning of this year, we have seen average high-rise construction costs increase by about 12% in the Greater Toronto Area and, for the balance of this year, some are predicting as much as 4% per month. What this means is that if you wait like the old days, you will likely see costs run away from you and you won't be able to finance your project based on the sales you do have in place.
So what you want to do is not go pens down. Keep going on drawings. Start buying construction (i.e. tendering). And work toward locking in as many of your costs as possible.
How much is ultimately up to you and the exact market conditions at the time. But I know a number of condominium developers now targeting at least 50% tendered, which means securing most of your key contracts: formwork, concrete & rebar supply, windows, M&E, and so on.
A lot of us are hoping that costs will eventually come down and follow certain commodities in the near term. But as our cost consultant effectively said to me this week, "just because the price of cold-formed steel has come down, do you really think you'll be able to walk into a BMW dealership and ask for a deep discount?"
Back in May, I wrote a post about time to market and managing costs in condominium projects. What I wrote then remains true and equally, if not more, important today. But given all the uncertainty that we are continuing to see in the market, I thought I would elaborate on a few points.
It used to be the case, when I first started working on condominium projects back in 2007 or so, that you would go pens down on your design drawings while you launched pre-sales and worked toward meeting your construction financing requirements.
Once you hit 50% sales, or maybe once you completely reached your financing hurdle, you would then call your architect back up and kindly ask them to get started on working drawings.
And the reason you did it this way was because working drawings are kind of expensive and so you wanted to make sure that your sales were going to be there. You were also trying to push as many of your costs out to after you had your construction loan in place so that you had a lower peak equity requirement.
You can't do this today.
Since the beginning of this year, we have seen average high-rise construction costs increase by about 12% in the Greater Toronto Area and, for the balance of this year, some are predicting as much as 4% per month. What this means is that if you wait like the old days, you will likely see costs run away from you and you won't be able to finance your project based on the sales you do have in place.
So what you want to do is not go pens down. Keep going on drawings. Start buying construction (i.e. tendering). And work toward locking in as many of your costs as possible.
How much is ultimately up to you and the exact market conditions at the time. But I know a number of condominium developers now targeting at least 50% tendered, which means securing most of your key contracts: formwork, concrete & rebar supply, windows, M&E, and so on.
A lot of us are hoping that costs will eventually come down and follow certain commodities in the near term. But as our cost consultant effectively said to me this week, "just because the price of cold-formed steel has come down, do you really think you'll be able to walk into a BMW dealership and ask for a deep discount?"