Many of you are probably acutely aware that the cost of lumber has risen dramatically over the last year. Builders are building and many people seem interested in renovating their home right now -- so demand is outstripping supply. But here is a chart from Fortune, with data from Random Lengths, showing you just how wild things have gotten. Back in April 2020, lumber was going for about $358 per thousand board feet, according to this data. As of the beginning of this month, the number had jumped to $1,048, which represents an all-time high and a 193% year-over-year increase. Who knows where pricing will go next, but the National Association of Home Builders is estimating that current pricing has added about $24,000 to the price of a typical new single-family home in the US.
Image: Fortune


Why do some buildings cost more to build than others? And how is it that some cities, as a whole, seem to build more cost effectively than others? Without getting into the specifics of how different markets work, I thought it would be valuable to outline some of the cost drivers that impact new developments. But keep in mind that this is by no means an exhaustive list. So, please feel free to add whatever I've missed to the comment section below.
Below-grade parking is hugely expensive. It's almost always a loss leader. You lose money building it. That's why parking ratios matter a great deal. If you're building in the suburbs at 1 to 1 parking vs. 0.2 in the core, you're simply building more of something that doesn't make money. There's also the question of whether you need to build a watertight below-grade, or if you can discharge any groundwater into the municipal infrastructure. Big cost difference.
Union vs. non-union construction labor.
Building stepbacks add cost and create additional complexity. To build more cost effectively, you really want repetition. But terraces are awesome. I get it.
Impact fees, development levies, and other government fees can vary widely across cities. As I've mentioned many times before on the blog, these line items can add up to 20-24% of the price of a new condominium here Toronto.
Time is expensive. One of the bigger line items in a development pro forma is financing interest charges. The longer things take, the more expensive the housing needs to be.
Markets are unique. Quebec, for example, has relatively low electricity rates. For this reason, it's pretty common for homes in Quebec to use electric heating, which is usually pretty cost effective to install. According to this 2019 study, 68% of Ontario households rely on natural gas heating. In Quebec, the number is only 5%.
Depending on what you're building next to, you may face additional costs. For example, if you're building right up against a rail line, you may need to construct a "crash wall" in order to safeguard against possible derailments and you'll probably need to up the STC rating on your windows because of the higher noise levels. These costs will not be insignificant.
In theory, land costs are supposed to be the residual claimant in a development pro forma. What that means is that you should back into your land value after calculating your projected revenue and considering all of your other development costs. If your revenue is lower, so too should be your land cost. Land cost as a percentage of total costs will, naturally, vary across different markets.


Yesterday I made a comment on Twitter about most people not understanding to what extent government bureaucracy inhibits the delivery of new housing in this city. It received a number of responses, including remarks about how development charges have also recently doubled and how this statement applies to pretty much every city out there. But there was also a comment about developers not being transparent and not properly explaining the impact to the public. In other words: please demystify the development pro forma. I thought that was a fair remark, and so this post is going to be a response to that comment.
Before I begin, it's important to keep in mind that most developers have investors. These investors put up most of the money required for a project and in turn they take most of the profits. However, there is typically a "promote" in place, which is just an incentive structure that pays the developer more of the profits (disproportionate to the cash they invested in the project) if they perform and hit certain return benchmarks. All of this is to say that developers aren't usually the ones holding all of the cash (which is what a lot of the public seems to think) and they are accountable to their investors to do what they said they would do.
Now let's run through the costs that make up a "typical" development pro forma. For this example, I am going to assume that we're talking about a 100,000 square foot mid-rise building; the kind that you might build and find along any one of Toronto's Avenues. If we were doing this in real life, we would get more precise with the areas and consider gross construction area, gross floor area (city definition), and the net saleable/rentable areas. But to keep the math simple, we will ignore these differences. That's the approach I'm going to take overall in the post. What you need to know, though, is that you have to pay to build the entire building, but you only get to collect revenue on a portion of it. That's why the "efficiency" of a building matters.
Land
The value of development land is a function of what you can build and the revenue you can ultimately collect. So location matters a great deal. Based on the latest high-density land report from Bullpen and Batory, the average price of an unzoned mid-rise site in the City of Toronto is about $231 psf. So let's assume a land cost for our project of $23.1 million. Assuming we can get land financing at 60% of the value of the land (loan-to-value), that would mean we're putting up $9.24 million of cash (plus a loan guarantee!) and borrowing $13.86 million to start our project. At 5.25% per annum (interest-only loan), our annual interest charges would be about $727,650. From now on forward, we're going to pay ~$60k in additional interest charges for every month that our project is delayed. Buckle up.
You should now begin to see why time is so valuable and why government bureaucracy can be so frustrating. As a developer, you're heavily incentivized to move things forward, whereas it can often feel like everyone around you is trying to deliberately erect roadblocks in order to slow you down and make your project more expensive to build. Oftentimes, it is because it is less risky for them to punt things down the road and not make a decision. That is not the case for us and our project.
Hard Costs
Onto construction (or hard) costs. As many of you know, these have risen dramatically over the last 4 to 5 years. On some of our projects, we have added over $100 psf in hard costs alone. Part of this has to do with a busy construction market and part of this has to do with new building requirements: watertight undergrounds, new Green Standards, and so on. For our project, which is on the small side, let's assume $360 psf for a total of $36 million. This would include our direct construction costs and our construction manager's overhead (general conditions). We should also prepare for some of the trades to decline to bid on our project because it is too small and not worth their time.
Soft Costs
Soft costs include everything from consultant costs and interest charges to government levies and management fees. Like everything in your pro forma, these absolutely need to be broken out line by line. Don't be lazy here. But for the purposes of this simplistic example, we're going to use 75% of hard costs, which works out to be $27 million (or $270 psf). When I first started out in the development business, the rule of thumb was closer to 25% of hard costs. But times have changed. Government fees, alone, can make up about 1/4 of the price of a new condo in Toronto.
Adding up all of these costs, we're at $861 psf or $86.1 million in costs. It's now time to consider the revenue side. $1,000 psf seems like a nice round number, so let's start there and assume we're going to sell our condos for that. Typically in Toronto, the price you pay is inclusive of HST, so that liability will need to be deducted from our revenue line. It's not a straight 13% because of the new home rebate, but the rebate also hasn't been properly indexed since it was introduced and so the liability could still be upwards of 10%. (This is worthy of a separate blog post.) The result is $900 psf in revenue and a margin on costs that is less than 5%. No sensible developer would want to do this project. One misstep (or development charge increase) and you're dead.
So let's increase our condo prices to $1,100 psf. Maybe that will work. In doing that, we get to a margin on costs that is nearly 15%. Okay, now we're in the range. But let's say we just got delayed by 6 months (boom, interest charges) and our hard costs turned out to be off by $15. They're actually working out to be $375 psf because of some new tariff and because the formworkers in the city are all tied up on bigger projects and couldn't give a shit about our cute little infill project. Now we're offside again in terms of our margin on costs. No problem, let's try and push condo prices a bit more. Is $1,150 achievable? Perhaps. But ideally, given the above, we would want to be at $1,200 psf just to be safe.
This is an overly simplistic example of the math that goes into a development pro forma. But hopefully it begins to show you (1) just how many moving parts there are in a development project and (2) the kind of pricing that is required in today's cost environment. Developers are reacting to the costs that they are being thrown and it is creating upward pressure on home prices. (See related post: Cost-plus pricing.) So far there has been enough elasticity in the market to absorb these price increases, but that may not always be the case. If you have questions about this post or disagree with any of my assumptions, feel free to leave a searing comment below.