Yesterday I made a comment on Twitter about most people not understanding to what extent government bureaucracy inhibits the delivery of new housing in this city. It received a number of responses, including remarks about how development charges have also recently doubled and how this statement applies to pretty much every city out there. But there was also a comment about developers not being transparent and not properly explaining the impact to the public. In other words: please demystify the development pro forma. I thought that was a fair remark, and so this post is going to be a response to that comment.
Before I begin, it's important to keep in mind that most developers have investors. These investors put up most of the money required for a project and in turn they take most of the profits. However, there is typically a "promote" in place, which is just an incentive structure that pays the developer more of the profits (disproportionate to the cash they invested in the project) if they perform and hit certain return benchmarks. All of this is to say that developers aren't usually the ones holding all of the cash (which is what a lot of the public seems to think) and they are accountable to their investors to do what they said they would do.
Now let's run through the costs that make up a "typical" development pro forma. For this example, I am going to assume that we're talking about a 100,000 square foot mid-rise building; the kind that you might build and find along any one of Toronto's Avenues. If we were doing this in real life, we would get more precise with the areas and consider gross construction area, gross floor area (city definition), and the net saleable/rentable areas. But to keep the math simple, we will ignore these differences. That's the approach I'm going to take overall in the post. What you need to know, though, is that you have to pay to build the entire building, but you only get to collect revenue on a portion of it. That's why the "efficiency" of a building matters.
Land
The value of development land is a function of what you can build and the revenue you can ultimately collect. So location matters a great deal. Based on the latest high-density land report from Bullpen and Batory, the average price of an unzoned mid-rise site in the City of Toronto is about $231 psf. So let's assume a land cost for our project of $23.1 million. Assuming we can get land financing at 60% of the value of the land (loan-to-value), that would mean we're putting up $9.24 million of cash (plus a loan guarantee!) and borrowing $13.86 million to start our project. At 5.25% per annum (interest-only loan), our annual interest charges would be about $727,650. From now on forward, we're going to pay ~$60k in additional interest charges for every month that our project is delayed. Buckle up.
You should now begin to see why time is so valuable and why government bureaucracy can be so frustrating. As a developer, you're heavily incentivized to move things forward, whereas it can often feel like everyone around you is trying to deliberately erect roadblocks in order to slow you down and make your project more expensive to build. Oftentimes, it is because it is less risky for them to punt things down the road and not make a decision. That is not the case for us and our project.
Hard Costs
Onto construction (or hard) costs. As many of you know, these have risen dramatically over the last 4 to 5 years. On some of our projects, we have added over $100 psf in hard costs alone. Part of this has to do with a busy construction market and part of this has to do with new building requirements: watertight undergrounds, new Green Standards, and so on. For our project, which is on the small side, let's assume $360 psf for a total of $36 million. This would include our direct construction costs and our construction manager's overhead (general conditions). We should also prepare for some of the trades to decline to bid on our project because it is too small and not worth their time.
Soft Costs
Soft costs include everything from consultant costs and interest charges to government levies and management fees. Like everything in your pro forma, these absolutely need to be broken out line by line. Don't be lazy here. But for the purposes of this simplistic example, we're going to use 75% of hard costs, which works out to be $27 million (or $270 psf). When I first started out in the development business, the rule of thumb was closer to 25% of hard costs. But times have changed. Government fees, alone, can make up about 1/4 of the price of a new condo in Toronto.
Adding up all of these costs, we're at $861 psf or $86.1 million in costs. It's now time to consider the revenue side. $1,000 psf seems like a nice round number, so let's start there and assume we're going to sell our condos for that. Typically in Toronto, the price you pay is inclusive of HST, so that liability will need to be deducted from our revenue line. It's not a straight 13% because of the new home rebate, but the rebate also hasn't been properly indexed since it was introduced and so the liability could still be upwards of 10%. (This is worthy of a separate blog post.) The result is $900 psf in revenue and a margin on costs that is less than 5%. No sensible developer would want to do this project. One misstep (or development charge increase) and you're dead.
So let's increase our condo prices to $1,100 psf. Maybe that will work. In doing that, we get to a margin on costs that is nearly 15%. Okay, now we're in the range. But let's say we just got delayed by 6 months (boom, interest charges) and our hard costs turned out to be off by $15. They're actually working out to be $375 psf because of some new tariff and because the formworkers in the city are all tied up on bigger projects and couldn't give a shit about our cute little infill project. Now we're offside again in terms of our margin on costs. No problem, let's try and push condo prices a bit more. Is $1,150 achievable? Perhaps. But ideally, given the above, we would want to be at $1,200 psf just to be safe.
This is an overly simplistic example of the math that goes into a development pro forma. But hopefully it begins to show you (1) just how many moving parts there are in a development project and (2) the kind of pricing that is required in today's cost environment. Developers are reacting to the costs that they are being thrown and it is creating upward pressure on home prices. (See related post: Cost-plus pricing.) So far there has been enough elasticity in the market to absorb these price increases, but that may not always be the case. If you have questions about this post or disagree with any of my assumptions, feel free to leave a searing comment below.
Photo by Marcos Paulo Prado on Unsplash
There's a narrative out there that all developers are uncreative and greedy, and if only they would start being more creative and generous, we could solve the housing affordability problem that is plaguing many (if not all) global cities. In other words, the solution to increasing the supply of low and middle incoming housing is simply a psychological reframing on the part of developers.
The problem with this mental model is that it ignores reality. Development happens on the margin. The market is competitive. It's difficult to find developable sites. And it's a challenge to make projects work. More often than not, you have to say no as a developer. No I can't buy this land. No I can't build housing here. And no the market will not support new office space here. Sorry, but no. (See cost-plus pricing.)
Development needs to give back. On the blog we usually call this city building. And that's because it implies a greater sense of civic responsibility. Developers aren't just building one-off buildings, they're building a city. I believe wholeheartedly in this. But the belief that projects can be saddled with an endless array of government fees and civic contributions is a problematic one. There are limits -- because markets have limits.
If only city building were that easy.

Yesterday I made a comment on Twitter about most people not understanding to what extent government bureaucracy inhibits the delivery of new housing in this city. It received a number of responses, including remarks about how development charges have also recently doubled and how this statement applies to pretty much every city out there. But there was also a comment about developers not being transparent and not properly explaining the impact to the public. In other words: please demystify the development pro forma. I thought that was a fair remark, and so this post is going to be a response to that comment.
Before I begin, it's important to keep in mind that most developers have investors. These investors put up most of the money required for a project and in turn they take most of the profits. However, there is typically a "promote" in place, which is just an incentive structure that pays the developer more of the profits (disproportionate to the cash they invested in the project) if they perform and hit certain return benchmarks. All of this is to say that developers aren't usually the ones holding all of the cash (which is what a lot of the public seems to think) and they are accountable to their investors to do what they said they would do.
Now let's run through the costs that make up a "typical" development pro forma. For this example, I am going to assume that we're talking about a 100,000 square foot mid-rise building; the kind that you might build and find along any one of Toronto's Avenues. If we were doing this in real life, we would get more precise with the areas and consider gross construction area, gross floor area (city definition), and the net saleable/rentable areas. But to keep the math simple, we will ignore these differences. That's the approach I'm going to take overall in the post. What you need to know, though, is that you have to pay to build the entire building, but you only get to collect revenue on a portion of it. That's why the "efficiency" of a building matters.
Land
The value of development land is a function of what you can build and the revenue you can ultimately collect. So location matters a great deal. Based on the latest high-density land report from Bullpen and Batory, the average price of an unzoned mid-rise site in the City of Toronto is about $231 psf. So let's assume a land cost for our project of $23.1 million. Assuming we can get land financing at 60% of the value of the land (loan-to-value), that would mean we're putting up $9.24 million of cash (plus a loan guarantee!) and borrowing $13.86 million to start our project. At 5.25% per annum (interest-only loan), our annual interest charges would be about $727,650. From now on forward, we're going to pay ~$60k in additional interest charges for every month that our project is delayed. Buckle up.
You should now begin to see why time is so valuable and why government bureaucracy can be so frustrating. As a developer, you're heavily incentivized to move things forward, whereas it can often feel like everyone around you is trying to deliberately erect roadblocks in order to slow you down and make your project more expensive to build. Oftentimes, it is because it is less risky for them to punt things down the road and not make a decision. That is not the case for us and our project.
Hard Costs
Onto construction (or hard) costs. As many of you know, these have risen dramatically over the last 4 to 5 years. On some of our projects, we have added over $100 psf in hard costs alone. Part of this has to do with a busy construction market and part of this has to do with new building requirements: watertight undergrounds, new Green Standards, and so on. For our project, which is on the small side, let's assume $360 psf for a total of $36 million. This would include our direct construction costs and our construction manager's overhead (general conditions). We should also prepare for some of the trades to decline to bid on our project because it is too small and not worth their time.
Soft Costs
Soft costs include everything from consultant costs and interest charges to government levies and management fees. Like everything in your pro forma, these absolutely need to be broken out line by line. Don't be lazy here. But for the purposes of this simplistic example, we're going to use 75% of hard costs, which works out to be $27 million (or $270 psf). When I first started out in the development business, the rule of thumb was closer to 25% of hard costs. But times have changed. Government fees, alone, can make up about 1/4 of the price of a new condo in Toronto.
Adding up all of these costs, we're at $861 psf or $86.1 million in costs. It's now time to consider the revenue side. $1,000 psf seems like a nice round number, so let's start there and assume we're going to sell our condos for that. Typically in Toronto, the price you pay is inclusive of HST, so that liability will need to be deducted from our revenue line. It's not a straight 13% because of the new home rebate, but the rebate also hasn't been properly indexed since it was introduced and so the liability could still be upwards of 10%. (This is worthy of a separate blog post.) The result is $900 psf in revenue and a margin on costs that is less than 5%. No sensible developer would want to do this project. One misstep (or development charge increase) and you're dead.
So let's increase our condo prices to $1,100 psf. Maybe that will work. In doing that, we get to a margin on costs that is nearly 15%. Okay, now we're in the range. But let's say we just got delayed by 6 months (boom, interest charges) and our hard costs turned out to be off by $15. They're actually working out to be $375 psf because of some new tariff and because the formworkers in the city are all tied up on bigger projects and couldn't give a shit about our cute little infill project. Now we're offside again in terms of our margin on costs. No problem, let's try and push condo prices a bit more. Is $1,150 achievable? Perhaps. But ideally, given the above, we would want to be at $1,200 psf just to be safe.
This is an overly simplistic example of the math that goes into a development pro forma. But hopefully it begins to show you (1) just how many moving parts there are in a development project and (2) the kind of pricing that is required in today's cost environment. Developers are reacting to the costs that they are being thrown and it is creating upward pressure on home prices. (See related post: Cost-plus pricing.) So far there has been enough elasticity in the market to absorb these price increases, but that may not always be the case. If you have questions about this post or disagree with any of my assumptions, feel free to leave a searing comment below.
Photo by Marcos Paulo Prado on Unsplash
There's a narrative out there that all developers are uncreative and greedy, and if only they would start being more creative and generous, we could solve the housing affordability problem that is plaguing many (if not all) global cities. In other words, the solution to increasing the supply of low and middle incoming housing is simply a psychological reframing on the part of developers.
The problem with this mental model is that it ignores reality. Development happens on the margin. The market is competitive. It's difficult to find developable sites. And it's a challenge to make projects work. More often than not, you have to say no as a developer. No I can't buy this land. No I can't build housing here. And no the market will not support new office space here. Sorry, but no. (See cost-plus pricing.)
Development needs to give back. On the blog we usually call this city building. And that's because it implies a greater sense of civic responsibility. Developers aren't just building one-off buildings, they're building a city. I believe wholeheartedly in this. But the belief that projects can be saddled with an endless array of government fees and civic contributions is a problematic one. There are limits -- because markets have limits.
If only city building were that easy.
Many, or perhaps most, developers I know have a minimum project size that they will work on. That's why you'll hear people say, "No, that project is too small. I need at least X square feet or Y number of units." Given that smaller scale development such as laneway housing and "the missing middle" are so in vogue today, I thought I would discuss some of the reasons why scale matters.
But first, it's worth mentioning that "laneway suites," as we have structured them here in Toronto, are intended to be built by individual homeowners and not by developers. The lots can't be severed and most lots will yield less than 1,000 square feet. So this is a bit of a unique circumstance. As most of you know, I am a big supporter of this initiative.
When you get into larger developer-led projects, it's a different ball game. For one, it's hard to even find sites. And good luck if you need to deal with multiple owners as part of an assembly. Most landowners have pricing expectations that do not even remotely align with "missing middle" level densities.
But assuming you've been able to find land at a reasonable price, you still have to contend with the fact that projects have a lot of fixed costs, as well as diseconomies of scale. In other words, there are schedule, cost, and resourcing considerations that won't change no matter how big or small you go. It's still going to take this long and cost this much, and you're still going to need a set of humans to manage it through.
This can then create a situation where there's not enough margin for error. The project is simply too small to absorb any shocks, such as an unforeseen delay or an unforeseen groundwater concern that is now adding millions to your project budget. There's a lot of risk with development and it's prudent to have contingency room. That's harder to do with smaller projects.
The other problem developers run into with smaller projects is that the construction subtrades also tend to think of them as smaller projects. They have their own set of fixed costs and margins to worry about. So unless you happen to catch them with an opening in their schedule, you run the risk of them telling you they're too busy or them giving you a stinky price, which is just another way of them saying they don't want the job.
On top of all this, there's minimum project size inflation. If capital is not a constraint, there's a tendency to want to do bigger projects (see above). And because the cost of everything keeps going up, it's simultaneously getting harder and harder to make smaller projects pencil; unless you, maybe, go ultra luxury and ultra exclusive. But that's kind of the opposite goal of this whole "missing middle" movement, is it not?
Photo by JOHN TOWNER on Unsplash
Many, or perhaps most, developers I know have a minimum project size that they will work on. That's why you'll hear people say, "No, that project is too small. I need at least X square feet or Y number of units." Given that smaller scale development such as laneway housing and "the missing middle" are so in vogue today, I thought I would discuss some of the reasons why scale matters.
But first, it's worth mentioning that "laneway suites," as we have structured them here in Toronto, are intended to be built by individual homeowners and not by developers. The lots can't be severed and most lots will yield less than 1,000 square feet. So this is a bit of a unique circumstance. As most of you know, I am a big supporter of this initiative.
When you get into larger developer-led projects, it's a different ball game. For one, it's hard to even find sites. And good luck if you need to deal with multiple owners as part of an assembly. Most landowners have pricing expectations that do not even remotely align with "missing middle" level densities.
But assuming you've been able to find land at a reasonable price, you still have to contend with the fact that projects have a lot of fixed costs, as well as diseconomies of scale. In other words, there are schedule, cost, and resourcing considerations that won't change no matter how big or small you go. It's still going to take this long and cost this much, and you're still going to need a set of humans to manage it through.
This can then create a situation where there's not enough margin for error. The project is simply too small to absorb any shocks, such as an unforeseen delay or an unforeseen groundwater concern that is now adding millions to your project budget. There's a lot of risk with development and it's prudent to have contingency room. That's harder to do with smaller projects.
The other problem developers run into with smaller projects is that the construction subtrades also tend to think of them as smaller projects. They have their own set of fixed costs and margins to worry about. So unless you happen to catch them with an opening in their schedule, you run the risk of them telling you they're too busy or them giving you a stinky price, which is just another way of them saying they don't want the job.
On top of all this, there's minimum project size inflation. If capital is not a constraint, there's a tendency to want to do bigger projects (see above). And because the cost of everything keeps going up, it's simultaneously getting harder and harder to make smaller projects pencil; unless you, maybe, go ultra luxury and ultra exclusive. But that's kind of the opposite goal of this whole "missing middle" movement, is it not?