Yesterday, February 28, 2025, the team installed the first piece of unitized curtain wall at One Delisle (on level two facing the outdoor amenity terrace and beside the indoor pool). Last year I was going around telling everyone that we would have glass up on the building in the first quarter of this year, and so I'm really glad that I was not made out to be a liar. Thanks team. This is a milestone date.
For those of you who maybe aren't familiar, there are two types of window systems that are commonly used in high-rise residential buildings. They are usually referred to as window wall and curtain wall. The former is more common in Toronto because it's, well, the cheapest; but there are curtain wall buildings other than One Delisle. Sometimes the same building might also use both systems. (In saying this, I'm specifically referring to the upper floors, because curtain wall is often used for ground-floor commercial spaces.)
The key difference is that window wall systems sit between floor slabs and get anchored at the sill and the head (the top of the slab on the bottom and the bottom of the slab on the top). Curtain wall systems, on the other hand, get anchored to the exterior slab edges and also "bypass" them. You can see that in the above photo. There are advantages and disadvantages to both systems, but generally speaking, curtain wall is viewed as higher quality, and the more expensive option.
In the case of One Delisle, we explored and were open to both options during the design process. But ultimately window wall just didn't seem like the right system to realize the unique geometries of this building. So we went with curtain wall, worked through a lengthy design-assist process with the subcontractor, built a bunch of mockups to make sure everything looked and worked well, and now it's being installed on site.
Level two is likely going to be the most challenging floor because of the double-height pool area. So I'll be sure to share more photos once it's all enclosed.
The typical way to buy or procure construction is create a set of drawings, put them out for tender to people who can build what is shown, select the lowest/best bidder, and then proceed with construction. This is commonly referred to as "design-bid-build." There are, of course, others ways to procure construction, but this is the traditional method. And in an idealized world, it would always work out very well for owners and developers. But in reality, it's a lot more complicated.
The important prerequisite for this method is a great set of drawings (more broadly, great contract documents). Because that is effectively the thing you are buying. Unfortunately, great drawing sets don't always happen and there are generally a few reasons for this. One possible scenario might be that you just don't have enough time to produce them. Maybe the market is hot and you want to start construction yesterday, or maybe you have some deadline to meet. Whatever the case, you're in a rush.
But the most likely scenario is that the drawings aren't great simply because the people doing them aren't good or because, hey, we are all only human. Things were missed, there are mistakes, and the drawings weren't fully coordinated across the various disciplines. There's no such thing as 100% perfect drawings. And that results in construction risk, because you've now bought things that are wrong and that will need to be corrected later.
Changes are costly. Later is also a suboptimal time for the simple fact that the price of construction depends on the current situation you happen to be in. Early on before a contract is awarded, buyers of construction have the most, or least some, leverage. The bid process is designed to be competitive and so bidders generally need to sharpen their pencils if they want to win the work. But once a job has been awarded and construction starts, that leverage flips.
Scope gaps and change orders become that much more expensive because, well, they can be. Switching costs are prohibitively high at this point. And it doesn't just work with scope additions. You will also be penalized for going in the opposite direction and removing scope items (i.e. credits). In these situations, you should expect to receive cents on the dollar back. This is one of the great asymmetries of construction pricing.
My point with this post is simply that the price of construction depends -- it depends on how and when you are buying it. It's a very opaque market and it's important to keep that in mind.

Hong Kong is one of the last cities in the world that still uses bamboo scaffolding for construction. Why? Well, for one thing, it grows very tall, and quickly (source):
Bamboo is one of the fastest-growing plants in the world, and in some cases can grow 60cm a day, and eventually 40 metres tall. Bamboo has thick underground roots called rhizomes, which can grow quickly, creating new shoots metres away.

And it's cell-like structure performs very well under compression:
Compared to steel, bamboo is much lighter, six times faster to erect and 12 times faster to dismantle. It’s also a fraction of the cost. Bamboo scaffolding doesn’t require sophisticated machinery or complex tools to erect, just skilled workers with nylon ties. If properly erected, bamboo scaffolding can be stronger than steel and far more flexible. The resulting structure is also easy to modify, if necessary. Bamboo scaffolding can be used for entire structures, or part of them. In Hong Kong it is common to see “bamboo balconies” jutting from the sides of buildings where renovations are being carried out on individual units, many floors up. A bamboo pole can also be cut to fit an awkward space, which is ideal for Hong Kong, where construction spaces can be tight amid the densely packed maze of buildings.

Yesterday, February 28, 2025, the team installed the first piece of unitized curtain wall at One Delisle (on level two facing the outdoor amenity terrace and beside the indoor pool). Last year I was going around telling everyone that we would have glass up on the building in the first quarter of this year, and so I'm really glad that I was not made out to be a liar. Thanks team. This is a milestone date.
For those of you who maybe aren't familiar, there are two types of window systems that are commonly used in high-rise residential buildings. They are usually referred to as window wall and curtain wall. The former is more common in Toronto because it's, well, the cheapest; but there are curtain wall buildings other than One Delisle. Sometimes the same building might also use both systems. (In saying this, I'm specifically referring to the upper floors, because curtain wall is often used for ground-floor commercial spaces.)
The key difference is that window wall systems sit between floor slabs and get anchored at the sill and the head (the top of the slab on the bottom and the bottom of the slab on the top). Curtain wall systems, on the other hand, get anchored to the exterior slab edges and also "bypass" them. You can see that in the above photo. There are advantages and disadvantages to both systems, but generally speaking, curtain wall is viewed as higher quality, and the more expensive option.
In the case of One Delisle, we explored and were open to both options during the design process. But ultimately window wall just didn't seem like the right system to realize the unique geometries of this building. So we went with curtain wall, worked through a lengthy design-assist process with the subcontractor, built a bunch of mockups to make sure everything looked and worked well, and now it's being installed on site.
Level two is likely going to be the most challenging floor because of the double-height pool area. So I'll be sure to share more photos once it's all enclosed.
The typical way to buy or procure construction is create a set of drawings, put them out for tender to people who can build what is shown, select the lowest/best bidder, and then proceed with construction. This is commonly referred to as "design-bid-build." There are, of course, others ways to procure construction, but this is the traditional method. And in an idealized world, it would always work out very well for owners and developers. But in reality, it's a lot more complicated.
The important prerequisite for this method is a great set of drawings (more broadly, great contract documents). Because that is effectively the thing you are buying. Unfortunately, great drawing sets don't always happen and there are generally a few reasons for this. One possible scenario might be that you just don't have enough time to produce them. Maybe the market is hot and you want to start construction yesterday, or maybe you have some deadline to meet. Whatever the case, you're in a rush.
But the most likely scenario is that the drawings aren't great simply because the people doing them aren't good or because, hey, we are all only human. Things were missed, there are mistakes, and the drawings weren't fully coordinated across the various disciplines. There's no such thing as 100% perfect drawings. And that results in construction risk, because you've now bought things that are wrong and that will need to be corrected later.
Changes are costly. Later is also a suboptimal time for the simple fact that the price of construction depends on the current situation you happen to be in. Early on before a contract is awarded, buyers of construction have the most, or least some, leverage. The bid process is designed to be competitive and so bidders generally need to sharpen their pencils if they want to win the work. But once a job has been awarded and construction starts, that leverage flips.
Scope gaps and change orders become that much more expensive because, well, they can be. Switching costs are prohibitively high at this point. And it doesn't just work with scope additions. You will also be penalized for going in the opposite direction and removing scope items (i.e. credits). In these situations, you should expect to receive cents on the dollar back. This is one of the great asymmetries of construction pricing.
My point with this post is simply that the price of construction depends -- it depends on how and when you are buying it. It's a very opaque market and it's important to keep that in mind.

Hong Kong is one of the last cities in the world that still uses bamboo scaffolding for construction. Why? Well, for one thing, it grows very tall, and quickly (source):
Bamboo is one of the fastest-growing plants in the world, and in some cases can grow 60cm a day, and eventually 40 metres tall. Bamboo has thick underground roots called rhizomes, which can grow quickly, creating new shoots metres away.

And it's cell-like structure performs very well under compression:
Compared to steel, bamboo is much lighter, six times faster to erect and 12 times faster to dismantle. It’s also a fraction of the cost. Bamboo scaffolding doesn’t require sophisticated machinery or complex tools to erect, just skilled workers with nylon ties. If properly erected, bamboo scaffolding can be stronger than steel and far more flexible. The resulting structure is also easy to modify, if necessary. Bamboo scaffolding can be used for entire structures, or part of them. In Hong Kong it is common to see “bamboo balconies” jutting from the sides of buildings where renovations are being carried out on individual units, many floors up. A bamboo pole can also be cut to fit an awkward space, which is ideal for Hong Kong, where construction spaces can be tight amid the densely packed maze of buildings.

But it's unclear how long this will remain true. Young people aren't learning the trade at the same rate as previous generations. And today, there are only 2,479 registered bamboo scaffolders left in Hong Kong. Assuming you have the nerves, the hardest part of the job is apparently the knot. It can take years to master.
If you're interested in this topic, I recommend you read this article. I found it fascinating.
Images: South China Morning Post

But it's unclear how long this will remain true. Young people aren't learning the trade at the same rate as previous generations. And today, there are only 2,479 registered bamboo scaffolders left in Hong Kong. Assuming you have the nerves, the hardest part of the job is apparently the knot. It can take years to master.
If you're interested in this topic, I recommend you read this article. I found it fascinating.