The most boring part of constructing a high-rise, like One Delisle, has got to be installing the shoring piles. Sure there are big rigs moving about on site but, for the most part, there's almost no visible progress. That is, until you start excavating. Then you get to see said piles and you also end up with a big hole, which is something.
Thankfully shoring works are now complete at One Delisle and we have started on the big hole part (see above photo from our rooftop cam). The next major milestone will be our "bottoming out," and that's when the tower crane will go up and our massive raft slab foundation will get poured. Visible progress is certainly more fun.